Case study: Dudley
Project completed: January 2020 (16 days from enquiry to loan granted)
The Client:
An established developer
purchased a property and also the adjoining unoccupied land. The view was to
create a number of ground-up developments on the land. The developer had
experience with constructing ground up projects, having built numerous other
residential properties within his portfolio.
The Property:
Planning application was
submitted to construct 4 x 3 bedroom properties which would also include
off-road parking facilities. Located within the in-demand area of Netherton in
Dudley, the properties will benefit from close proximity to a range of
amenities and very good motorway links to Birmingham, and the rest of the UK.
The Challenge:
Initially the adjoining car park
was not owned by the developer, but on transacting on this with his own funds
to progress the project, he then required a development loan from Mint Bridging
to fund the works. The developer had their contractors in place with a budget
outlining their ambitious schedule of works, and all costs, which they
expressed were achievable. The borrower was looking to construct the properties
within 12 months, all of which were to be finished to a good standard ready for
sale at loan exit.
The Solution:
Mint Bridging was able to provide
a loan of £560,000 over a 12 month term, with a first charge on the land and
the developer’s residential property. Mint included a contingency within the
loan which was to be separated equally amongst each of the development drawn-downs,
should this be needed. Also included in the facility was an additional extension
duration at the end of their expected completion date, in order to provide time
for the sale of the properties.
The Outcome:
The borrower achieved their
completion date goal, alongside sales agreed on all four properties prior to
the project finishing. The properties were delivered to a high standard and all
achieved an asking price, above the expected pre-completion market value.
There was an unforeseen issue
with the new purchasers all buying under the “Help-to-Buy scheme.” This meant
the borrower did see completion times exceed far longer than expected. Mint
Bridging was able to work with the developer to extend the loan, giving capital
reductions as the sales happened. This reduced risk since the sales completed,
for the remaining period prior to the exit.
No comments:
Post a Comment